We are getting close to completing the B-9 and switching over to the F-9. We have a few projects that are still lingering before we do that though; re pouring cart paths, burying spoils that are too rocky to reuse, seeding the water diversion construction area, removing a few stumps, rolling all of the trench lines, and some sod projects.
We are still waiting on the last section of our wet well to be delivered so that we can start working on the pump station. hopefully we will have it up and running by the end of January. Our head count should be close to about 800 installed currently.