Monday, November 28, 2016

Irrigation installation progress report week 3

The goal for week three was to complete the section from hole #10 through hole #13.  I believe that that goal was reached.  #13 is about 85% complete but the crew was able to get all of the main lines trenched and laid on n#14 which was not in the projection.  That trade off leads me to believe that the target was met .
We were getting ready to start on the wet well structure last week but a chance of rain came in and delayed the start of that project.  Thanksgiving didn't help the timeline either.  And now we have serious chances for rain this week, which we need desperately.  We may not get to dig for the wet well until late this week.
The crew really hit a stumbling block on #10 with all of the rock.  Without that issue I think that they would have blown their timeline out of the water.  They should be in good soil for the remainder of the back nine so it should move pretty rapidly.
This morning our consultant,Trevor Holman, is laying out the head spacing on hole #14.  He will probably finish marking the back nine holes this week

No comments:

Post a Comment