Friday, January 20, 2017

Irrigation system update 1-20-17

Well the first part of 2017 has not been kind to us between the rock and the rain.  Last night we got 1.5" of rainfall onto an already saturated golf course.  The last 8 months have truly been feast or famine with regards to precipitation. 
On the plus side we are officially making the flip from front nine to the back nine for golf play tomorrow.  Unfortunately, we are forecast to get 0.5" of rainfall both days this weekend.  On the negative side we will be primarily Cart Path Only for the next 2 months.
We started piping on the front nine this week.  We have run into some rock on #8, as expected, and it has slowed the main line progress a little.  On the flip side the heads and lateral lines have been installed on #8 and most of #9.  The 2nd 10" main line that goes by the practice green got stalled by a big rock that we were not expecting.
In the positive column we have the completed wet well which looks like a small rock mountain.  I am hoping to pour a pad on it next week.  That's just one step closer to installing the, still unnamed, pump station. 
Also, we got the first and largest road bore completed yesterday.  It is the main trunk line, 12", from the pump station to #13.  We have 4 more to complete. 
We changed some of the concrete entrances and exits to roadways.  They used to be a 45 degree curb and gutter to cart path.  Now they are a more gentle transition from road to path and vice versa.  Also, we have been repairing some areas of the path that were really bad in the past. 