Thursday, April 6, 2017
Course Alterations for 2017
The first thing that we did was course yardage. This has been one of our most common complaints in the past. Well, we have added yardage tags to 350 sprinkler heads. I feel like we are so well marked that we might remove the blue red and black pavers in the fairways and posts at the path.
Hole Number 6 had the most noticeable changes. First off the left greenside bunker has been filled in. I still believe that it was one of the hardest situational shots on the course, unless you were smart enough to putt out of it. Next the front right greenside bunker is in the process of a face-lift. We have removed the steep face and are in the process of regarding the base. We will drain it, line it and add some new sand and were good to go. Then we opened up the exit area back to the path. It used to be about 5 yards wide between berms. Now you could drive the space shuttle through the exit area of the hole. I hope this allows for better traffic wear patterns.
On hole 8 we had the, while structurally sound, clunky bridge that I built removed. In its place is a concrete cart path bridge that wont knock out your teeth when you drive over it. We also removed the old grass bunker left of the fairway.
On hole 10 we extended the rock walls surrounding the fairways. Also, we filled in the 3 grass bunkers on the left side of the fairways. Lastly we added a more friendly Ladies tee that is waiting for sod.
On Hole 12 we got rid of the dip in the cart path that went through the creek bed. We replaced it with a new cart path bridge.
On hole #14 we removed the left side fairway bunker.
On hole #17 we removed the old grass bunker on the right side of the fairway. It will finish its transition into a new Ladies tee.
On hole 18 you will notice that you are driving through the water in the spillway. That is because of the new stream that has been routed through the 18th hole.
Hopefully I have not forgot any of the new features but it is entirely possible that I have.
Irrigation Renovation Update 4-6-17
I have been running water for about a week now. I am trying to find bugs in the system, test capabilities and find programming thresholds and faults. Every morning I am riding the course looking for weeping heads, heads that are stuck on or other anomalies that may have taken place from the night previous. Hopefully the punch list made each morning will diminish with time. I have heard from some residents about sprinklers hitting decks or patios. If you have one of these issues please contact me and let me know. I will not get to see every one of the 1,700 heads run. I have moved our watering times to 10:00 PM so there will be less likelihood of something hitting a deck when you might be eating dinner. I have had programs running at 7:00 PM and 6:00 AM so that I can see or get feedback on the process but it is time to put them on in the dark.
The parking lot is starting to get vacated just in time for tournament season. We still have a lot of pipe to get out and some other items. Thank you to the neighbors who were very patient with us while we stopped traffic to load the Semi trucks on Calumet Trace with equipment, you were very patient with us.
While the project is winding down there is still a lot to do. there are a lot of areas that have been torn up and need to be repaired. We have been re seeding areas this week and are waiting on some sod to come in any day now. We will still have a small construction crew here for another 3-4 weeks cleaning up and helping fix scars and smoothing out rough areas.
Once again, Thank You to Nutt Construction, Aqua Turf International Consulting, Rainbird Golf Products, Keeling Co., Ole South Excavation, the Residents of Indian Hills Subdivision and All of our golfers.
Wednesday, March 8, 2017
Irrigation Renovation Update March 8th
There are only 2 areas left to irrigate. The club grounds with a res/com system and the nursery area which is about the size of a par 4. The nursery area runs parallel #2 on the other side of the rail road tracks. Apparently this area was once intended to be part of the course but for one reason or another it was abandoned. It has been a bone yard or a dumping ground for the last 30 years. The whole thing was an over grown cedar thicket. So we had it cleared out with a grinding machine. We found that there had been some clearing and shaping that took place somewhere in the past. Piles of boulders and piles of quality tee soil piled up in areas. It was really pretty cool to uncover. I would love to eventually have a full sod nursery with An acre of bent, fescue, bermuda, and zoysia at some point in the future.
The pump is in place and the pump house is dried in. Brick is scheduled for the exterior on Monday and the electricity will hopefully be run this week. Would love to be blowing out installed lines in a week.
We have some cleanup still going on on the front nine. I would hope to get all 18 holes back open for play on next Saturday. We still have a lot of concrete cuts to pour and rolling to do though.
Friday, January 20, 2017
Irrigation system update 1-20-17
On the plus side we are officially making the flip from front nine to the back nine for golf play tomorrow. Unfortunately, we are forecast to get 0.5" of rainfall both days this weekend. On the negative side we will be primarily Cart Path Only for the next 2 months.
We started piping on the front nine this week. We have run into some rock on #8, as expected, and it has slowed the main line progress a little. On the flip side the heads and lateral lines have been installed on #8 and most of #9. The 2nd 10" main line that goes by the practice green got stalled by a big rock that we were not expecting.
In the positive column we have the completed wet well which looks like a small rock mountain. I am hoping to pour a pad on it next week. That's just one step closer to installing the, still unnamed, pump station.
Also, we got the first and largest road bore completed yesterday. It is the main trunk line, 12", from the pump station to #13. We have 4 more to complete.
We changed some of the concrete entrances and exits to roadways. They used to be a 45 degree curb and gutter to cart path. Now they are a more gentle transition from road to path and vice versa. Also, we have been repairing some areas of the path that were really bad in the past.
Monday, November 28, 2016
Irrigation installation progress report week 3
We were getting ready to start on the wet well structure last week but a chance of rain came in and delayed the start of that project. Thanksgiving didn't help the timeline either. And now we have serious chances for rain this week, which we need desperately. We may not get to dig for the wet well until late this week.
The crew really hit a stumbling block on #10 with all of the rock. Without that issue I think that they would have blown their timeline out of the water. They should be in good soil for the remainder of the back nine so it should move pretty rapidly.
This morning our consultant,Trevor Holman, is laying out the head spacing on hole #14. He will probably finish marking the back nine holes this week
Monday, November 21, 2016
Irrigation renovation progress report Week 2
The current location of the crew with mainline is #12. The lateral crews are wrapping up the fairway on the 11th hole.
The machine appears to be gaining some steam. I hope that we start to see about a hole and a half completed per week. When I use the term completed I am referring to pipe in the ground with heads in place. There is still work to be done on the completed holes. Debris piles must be removed, boulders removed, cart path cuts have to be re-poured, plow lines have to be rolled out, and many other cleanup projects must be completed.
Projections for next week. I hope to see #12 Tee, Fairway and Natural Area completed. Also I am hopeful to see some work done on #13 Fairway and Green also. This is a large completion list for our progress so far but the closer we move toward #14 the higher quality the soil will be.
Also I am sure if you have visited the course in the last few days you have noticed the pond on #18 getting very low. We are pumping it down in order to install the new wet well and intake line that are the base for our awesome new pump station.
Sunday, November 23, 2014
What do you do in the winter?
Well, it's the week of Thanksgiving and I'm currently on vacation with my family at the beach and I still can't stop working. I am taking a break from creating my budget for 2015 right now. That is one of my big tasks for the month of November. This also involves the process of early ordering chemicals for 2015, which means that I have to have an agronomic plan in place for 2015 by this point. I'm not going to go too deep into what I, personally, have to get done.
I will come up with ideas of things that I would like to change all year long. Hopefully when I have that idea I have my trusty voice recorder with me so I can make a "note to self" and remind myself later. Some of the things that we work on are carry over jobs that are just too big for our staff to complete in one season. We also have repeat jobs that we have to do the same at a certain time every winter.
I will try to outline the jobs that we will be doing this season excluding keeping up the golf course, which does not stop getting done,
Single Season Jobs
tree work
debris removal
opening up the traffic areas on #6
building new tees on #11 and #17
converting the monument Tee signs into flush in ground tee signs
fixing the maintenance shop ceiling
cut back the bradford pears in the parking lots
relocate and identify the correct teeing areas from the score card
adding new heat to pump station
Carry over jobs
clearing out the riverbank on #8, 16, 17, 18
rebuilding bunkers
repair poor sections of cart path
Repeat jobs
spray roundup and pre emergent on entire course
repaint all tee markers on course
repaint all hazard markers on course
repaint all OB stakes on course
leaf removal in late fall/early winter
re seal wood products out on course benches, cooler stands, trash cans
reorganize the maintenance yard area
clean out and re insulate bird houses huts and nesting areas
working on repairing faulty wiring in the irrigation system
repainting the pump station
I know that I am missing a few in there but even with the amount of repeat jobs we have a lot to accomplish in an off season with a limited staff, not to mention working on the interior of the club house when it needs attention. And I know that I will come up with more stuff that I want to complete because I do suffer from my eyes being bigger than my stomach frequently.
With all of that said, that's what we will be doing this winter.
Wednesday, February 26, 2014
Stump Removal
Friday, December 6, 2013
Number 7 Water Feature is Back!!!!
![]() |
| The Problem Hole is 2 feet wide |
The pond was as low as it was going to get and we were in the middle of the dry season (late October). We Brought in an Excavator to search to find the problem. The more we dug the wetter the hole got. We were running two 2 inch trash pumps to keep the water out and we could barely keep up with the water coming out of the fissure I took 3 attempts with the excavator to clean up the hole. At this point we were getting out of the dry season and having to schedule around weather events, but we finally got close enough to the fissure to attempt to plug it with the Bentonite.
link to a video of the underground stream in action
Thursday, December 5, 2013
Tree Removal
We are currently working on Hole #10. We have removed 4 large Cedar trees. the first was closest to the tees on the right side of the cart path and overhung the path. I did not want to remove this tree but it had a lateral crack or split through the limb over the path and was getting ready to come down naturally.
| The before picture from #10 |
The heavy cedars were creating the most of the shade problem in the area. There are still about 5 Oaks in the area and one Hackberry. There are still obstacles that you need to avoid as a golfer on that side of the hole. Hopefully next year there will also be rough there to hit from.
| The after picture from #10 |
Tuesday, October 15, 2013
Fall Aerification
Here's the "Flip Book"
I hope that you can see the progress as well as I can. Again this is still a new process of documenting these types of events, and I learn something new about it every time I try.
Monday, September 16, 2013
!!! UPDATE !!! Range Tee Changes
Friday, August 23, 2013
Rainy Day Jobs
We think that they are a more accurate representation of the actual object. The markers are made of composite deck board that are cut in to the shape of an arrowhead. then we use an angle grinder to sharpen the edges. Then we use a stationary grinding stone to add some character to the beveled edges. The final color will probably end up being a natural grey stone color, not black. Lastly we took some string line and soaked it in a can of wood stain and used it for the serving string that would connect the arrowhead to the shaft of the arrow. We have not completely decided how we will distinguish the markers from one another. But we are leaning towards a dot of color on the side about 1.5" in diameter located on the cart path side of the marker.
Please remember that a lot of hard work goes into most of the materials that we have out on the course. So, please treat it kindly. Don't hit them with clubs, don't throw them in various locations and Please don't take them home with you.
Wednesday, July 24, 2013
Pond Management
Tuesday, October 23, 2012
New Natural Areas
Tuesday, April 10, 2012
New Bunkers
There was also a bunker eliminated in this round of work. #1 green side bunker has been removed. It is now rough height Bermudagrass. It is basically a catchers mitt now. If you come up short in that area now you will have a very difficult up and down. I did like the placement of the bunker on #1, but the slope was just too dramatic for a bunker here.
We also laid a lot of sod in other areas while we were finishing up the renovated and removed bunkers. We re sodded the exit from #6 fairway back to the cart path. This area has been a continual "thorn in the side " for us. We also sodded the removed bunker on #11 fairway, the exit to the cart path from the fairway on #12, and we also did some cleanup work behind the pump house on #18 where we did some repair work this winter.
We have already started working on the next round of bunker renovations. #'s 3 and 5 have already been shelled out and we are ready to begin cutting drain lines in them. we hope to button them up soon.
Friday, January 20, 2012
Aububon Projects
Thursday, September 22, 2011
State of the Union Address
Tuesday, January 18, 2011
It's Winter
The future shape of # 7 Bunker.
Monday, November 29, 2010
Bunker Renovation
The process of fixing a bunker is not as easy as most people think. I often get the question, “Can’t you just put some sand in the bunkers?” Simple answer, No. Full answer, we can’t do that because the pretty, expensive, playable sand that we put in the bunker will integrate with the soil like sand that we have in our bunkers now and be ruined in the first heavy rainfall we get. There are steps to properly rebuilding a bunker. The first step I take is finding the drainage out fall area. Without proper drainage bunkers become ponds quickly. After the outfall area is found we will redefine the edges of the bunker. We will have no more steep sloped faces on our bunkers. The steep faces are too labor intensive. The next step is creating the drain system; there are many different methods to drainage. I am going to go with the tried and true method of herring bone drainage. It is the same style that we used on # 11 fairway bunker and it has preformed beautifully. After the drainage is cut and cleaned the liners can be installed. Liners are a method of diverting water without diverting sand with it, and they are a barrier between sand and soil to prevent contamination of the sand.
The elimination process will consist of filling the existing bunker with topsoil to conform to the existing topography. Then in the spring we will come back with bermudagrass sod and cover the topsoil areas.
This project will be a major improvement to the golf course and will also greatly enhance play.